Steps 3 and 4 of the steel structure engineering construction plan: roofing, wall system installation and completion acceptance
Category: Industry News
Time:2020-07-08
The previous two articles also explained the steel structure engineering construction, steel structure foundation engineering and steel structure hoisting, and then Xiaobian will continue to explain the roofing, wall system and completion acceptance criteria for you!
(1) Installation of purlins and support systems
The purlins and supporting systems should be cooperated with the steel structure hoisting to carry out cross operations and flow construction.
The steel structure engineering purlin installation can be installed by pulley borrowing method, and the installation requires the screw hole position to be aligned and the tightening degree is reasonable. According to the specifications and use parts of the purlins, it is installed by manually hanging to the corresponding position of the roof or wall façade.
The support should be installed in time according to the requirements of the regulations, and the installation position is required to be accurate to meet the design requirements to ensure the overall rigidity and stability of the steel structure.
Immediately after the lifting is completed, the verticality and horizontality between the components should be adjusted, and in order to ensure the correct alignment between the continuous components, it is necessary to install the inter-column support and horizontal support and adjust these supports in time. Adjust the column brace should make one side of the column brace lock the other side relaxed, when the column has reached the verticality, the column brace should finally lock to the "taut" condition, but do not put the diagonal brace lock too tight and damage the member. From the eaves to the ridge, the roof is kept vertical by adjusting the horizontal support and aligning the roof beams with the ridge point as the center point. In short, the diagonal brace can only be locked after all components to be adjusted vertically and squarely.
Generally, the beam braces are attached to the roof beams on the ground, and bolts are used to connect to the roof purlins after hoisting. The table angle is fixed by expansion bolts, and the gable angle is installed from the cornice to the ridge and preferably fixed to the lower wing edge of the gable purlin.
When installing roof, wall tie rods andtie rods, the horizontality of the purlins should be adjusted in time, and the bending and deformation of the purlins caused by transportation or stacking should be corrected.
Leveling: Before the purlin installation, the purlin support point should be measured and leveled, the low point should be appropriately raised, and the height difference between the purlins should be strictly controlled within ±5mm.
Bullet line: The purlin bearing point should be fixed according to the support point positionrequired by the design, so the support point should be ejected (or scratched) out of the center position with ink line for the installation and positioning of the purlin to ensure the straightness of the purlin and the layout according to the purlin layout drawing.
Vertical lifting and arrangement: after properly bundling the purlins according to the layout needs, use a car crane to lift them to the designated position, and then arrange the purlins according to the drawings and purlin specifications to achieve reasonable stacking and correct arrangement (or lift the purlins of various specifications in place according to the drawings on the construction site, and borrow pulleys to lift them to the roof).
Lap joint: the installer according to the layout of the purlin according to the requirements of the drawing bolt connection, before connection should measure the fixed point position to ensure that the spacing, position is correct, straightness is not more than 6mm, height difference is not more than 5mm.
(2) Installation of roof panels and edging panels
There is no joint longitudinally for the roof panel, and the gable end on one side of the construction site should leave the roof panel production site and the finished product stacking site. The roof panels are transported to the roof by lifting, and the installation sequence should take into account the dominant wind direction in the area, and the installation is laid from one end of the plant step by step. The order of roof panel construction is determined according to the site conditions.
First install the first board against the gable side, when the first roof panel is fixed in place, pull a continuous alignment line at the roof cornice, this line and the first roof panel will become the guiding reference, which is convenient for the rapid installation and correction of subsequent roof panels, and then each roof area should be regularly tested during installation, by measuring the width of the fixed roof panel. Measure once at the ridgeline (or the top of the board) and once at the cornice (or the bottom of the board) to ensure that there is no movement and fan, and to ensure the parallelism and perpendicularity of the roof panels.
The steel structure engineering roof panel bending parts mainly include ridge internal and external edges, sealing plates and ridge gable cornices edges, etc. (pay attention to the order of construction), these color plate bending parts and color plate connection with aluminum rivets, color steel bending parts accessories should be neat, beautiful, meet the waterproof effect, after all fixed, with sealant after a section and then gently wipe to make even, flashing board and other waterproof points should be coated with sealant.
1. Roof panel installation:
Construction sequence:
The construction sequence is determined by the order in which the structure is conditioned, and the normal construction sequence develops from one end of the roof to the other.
Construction procedure:
According to the structure of the metal roofing system and the installation program of the system, the construction procedure of this project is shown in the figure below
Apedestrian walkway is set up on the purlins to ensure construction safety and construction progress.
When installing, use a crane to lift the board to the roof (manual lifting method can also be used). The lifting belt must be used for flexible lifting such as nylon belt or cloth belt, and steel belt must not be used. Protective wooden strips should be inserted between the package and the sling or packaging to prevent deformation of the board edge. The handling of the plate should be handled gently, avoid bumping, and it is strictly forbidden to mop the floor to avoid damaging the board. Before installation, the surface of the board should be cleaned first, and then check whether there is residue on the board surface, if so, clean the residue with detergent and water, and wipe the moisture on the surface with a dry cloth.
The laying direction of theboard must be laid in the reverse dominant direction, and the line must be bounced at any time during the installation of the roof panel to prevent accumulated errors. During roof panel installation, the ridge cover and waterproof plug (or roof panel bend) installation must keep up at the same time. The slab is sensitive to concentrated load, so during the construction of roof color panels, the construction personnel must not gather together to avoid local damage of the slab caused by concentrated load. When installing the roof panel, it is installed while lifting, at least the board on the lifting roof must be installed on the same day, and all the boards that are not installed on the same day must take corresponding measures to prevent falling.
Quality requirements: the size of the profiled plate is correct, the surface is clean, the undetectable concave and creased, the joint is straight, the vertical and horizontal lap is in a straight line, the seam is uniform and neat, and there is no warping and error-free drilling.
2. Installation of roof ridge plugs (or roof panel bends) and roof ridge panels
Pay-off positioning: the starting reference line of the first ridge plate, and the installation control line of the ridge plug (or roof panel bend) and the two sides of the ridge plug are determined in the installation direction.
Install the roof ridge plugging plate (or roof panel bend), the contact part between the plugging plate and the profile plate is fully coated with waterproof glue, and then install, seal the plug with waterproof glue to prevent leakage, and install subsequent plugs in turn. Install the first ridgeplate and adjust the positioning according to the starting reference and control line installation of the first ridgeplate. Measure the positioning plate of the bent water baffle on the ridgeplate, cut it with scissors, fix the roof plate with the specified pull rivets on the profile plate, seal the fixing with waterproof glue, and bend the water baffle according to the bending positioning line of the delineated bending positioning line.
3. Installationof flooding, wrapping corners and expansion joint covers:
The pay-off determines the starting reference line of the first block, and determines the control line of the two sides of the board in the installation direction. Install the first piece, install the second plate according to the reference line and control line to adjust the positioning, fix it on the fixing plate, and seal the fixing with waterproof glue to prevent leakage. On the first plate, measure and mark the lap positioning line between the second plate and the first plate, apply waterproof glue to the lap part of the board, install the second plate to adjust the positioning, fix the fixing and apply waterproof glue seal, and install the second plate and subsequent boards in turn.
(3) Gutter installation
This project adopts galvanized steel gutter drainage, and the connection method between the two sections of gutter is butt welding.
Gutter butt welding. Before the gutter docking, the cutting mouth is polished clean, and the gap between the weld seams should not exceed 1mm when docking, and spot welding can be carried out only after confirming that the requirements are met. In order to improve the construction efficiency, several sections of gutter can be assembled together on the ground and then installed, which can greatly reduce the aerial work and improve the quality of the gutter splicing.
Open downhole holes. After installing a section of gutter, several holes should be drilled in the middle of the designed downspout position to avoid water storage in the gutter and affect the construction. After the plate corresponding to the gutter is installed, the sinkhole must be opened in time. Formal downhole with hollow drill cutter cut-out or cut-out machine opening
(4) Wall panel installation
In principle, the wall panel is constructed with tool-type external hanging mobile aluminum tube scaffolding or simple hanging frame. When installing, attention should be paid to the horizontal and vertical operation deviations to ensure horizontal and vertical, and at the same time, when installing the upper wall panel, the bottom wall purlin should be supported by square wood under it and reviewed. Before installing the exterior wall panel, install the upper flooding of the wall system, the flooding of the window and door side and the edge of the platform at the junction with the brick wall, and then install the lower flashing edging and the yin and yang corner boards after the wall panel is installed.
(5) Paint construction
After the steel frame is welded, the paint construction team enters the site to paint the on-site paint. Before painting, the components must be cleaned and sanded to ensure that the weld is flat. Then use anti-rust primer to prime, and wait 24 hours before topcoat. Other construction processes are the same as the painting process in the factory.
(6) Door and window engineering
After the door and window openingsare formed, the door and window construction team should review the size of the on-site openings and make the doors and windows according to the actual measured data. Install in the order of first sash and then sash. When the gap between the window frame and the hole is large, it should be filled with a foaming agent before gluing. The glass glue should be applied in place and evenly to ensure good sealing and look and feel quality.
4. Completion acceptance
Preparation for completion acceptance: do a good job of data sorting in accordance with specifications and design requirements; According to the principle of first team inspection, then project department inspection, and finally general contractor, supervision and owner inspection, the construction quality is accepted, and the unqualified process must be rectified in time, and the same problem must not be brought to the next inspection procedure.
Organize completion acceptance: invite local quality inspection stations to work with the five parties to inspect and accept the project data and construction quality. After acceptance, do a good job of binding and archiving materials.
Keywords: Steps 3 and 4 of the steel structure engineering construction plan: roofing, wall system installation and completion acceptance
Related Information
Company News
-
Xirong "brand Great Wall board - Southwest Great Wall in the field of home decoration insulation board
Time:2024-08-06
-
Welcome the bid for steel structure enclosure materials for the "West China Intelligent Assembly Base Project" at the beginning of 2024
Time:2024-04-15
-
Shifang Navigation Industrial Park - Tianhe Solar's 160000 ㎡ Steel Bar Truss Floor Support Plate Project Celebrates Completion
Time:2024-04-15
-
Congratulations on winning the bid for "Meikou Chengdu Qingbaijiang Cold Chain Supply Chain Construction Project"
Time:2022-11-08
-
The Zerui comprehensive insurance project started successfully
Time:2022-11-08
-
The 200,000 square meters of truss floor bearing materials for the Chengdu Aviation Industrial Park project continued to be delivered
Time:2022-11-07
-
Notice of the Department of Housing and Urban-Rural Development of Sichuan Province on the use of the "Certificate of Qualification for Job Training and Assessment of Professionals in the Field of Housing and Urban-Rural Construction"
Time:2021-12-28
-
Notice of the General Office of the Ministry of Housing and Urban-Rural Development on matters related to the unified renewal of the qualifications of construction project enterprises
Time:2021-12-18
-
A pearl of performance on the prairie
Time:2021-09-06
-
Celebrating the 100th anniversary of the founding of the party, the Chengdu metal cloud merchant headquarters and regional center project started construction in the scorching summer and braved the wind and rain
Time:2021-07-12
-
Celebrating Sichuan Qingyuan Construction Engineering settled in the "China Building Science and Technology Conference and Construction Expo"
Time:2021-07-05
-
Happy birthday!
Time:2021-07-01
-
Morning meeting
Time:2021-06-23
-
2021 company safety fire drill
Time:2021-06-17
-
Leaders of Wuxi Binhu District visited the chairman unit of Chengdu Yancheng Chamber of Commerce for inspection
Time:2021-06-04
-
The large-scale cross-line municipal steel bridge project in Kaili City, Qiandongnan Prefecture, Guizhou Province was officially hoisted
Time:2020-06-03
-
Greenland Southwest Operation and Settlement Center for Global Imported Commodities reached a cooperation with Xirong Group
Time:2020-06-03
-
Silhouette of the steel structure construction site of PepsiCo Food (Sichuan) production base construction project
Time:2020-06-03
-
Zhengxi Robot R&D and Manufacturing Base Construction Project The resumption of construction work was carried out in an orderly manner
Time:2020-06-03
-
Qingbaijiang Sino-Ocean International Cold Chain E-commerce Logistics Park steel structure project welcomes the resumption of work
Time:2020-06-03
-
Sichuan TV Science and Education Channel "Impact Sichuan" interviewed Sichuan Qingyuan Construction Engineering Co., Ltd
Time:2020-06-03
-
On February 20, 2020, the leaders of the District CPPCC and the Industrial Management Committee inspected the resumption of work and epidemic prevention in our company
Time:2020-06-03
-
Notice of official resumption of work
Time:2020-06-03
-
Silhouette of the steel structure construction site of PepsiCo Food (Sichuan) production base construction project
Time:2020-04-24
Industry News
-
Carey is about to give birth to a new landmark of Internet celebrities, panoramic VR sneak peek!
Time:2020-07-08
-
Xirong takes you to understand the five characteristics of doors and windows
Time:2020-07-08
-
Xi Rong tells you how steel is developing in the Chinese market?
Time:2020-07-08
-
The steel structure engineering company reminds you of the processing precautions of the color coated plate
Time:2020-07-08
-
Xirong Steel Structure Company announces industry trends
Time:2020-07-08
-
What problems do you need to pay attention to when building color steel?
Time:2020-07-08
-
Steel structure engineering company takes you to focus on the development trend of color steel plate
Time:2020-07-08
-
Analysis of the current situation of marketing channels in China's construction machinery industry
Time:2020-07-08
-
The steel structure engineering company summarizes the use characteristics of galvanized channel steel for you
Time:2020-07-08
-
The steel structure engineering company tells you how to go out of the domestic steel structure
Time:2020-07-08
-
Steel structure engineering company tells you why China's steel prices are rising again?
Time:2020-07-08
-
Do you understand the "breaking" and "standing" of the development of the steel industry?
Time:2020-07-08
-
Xirong takes you to understand the "three magic weapons" in steel trade marketing
Time:2020-07-08
-
Xirong talks about CAI steel market will turn salted fish over?
Time:2020-07-08
-
Steel structure engineering company analysis steel price rise is difficult to end
Time:2020-07-08
-
How can the steel industry break the "curse" of financial difficulties?
Time:2020-07-08
-
Xirong analyzes modern steel structure buildings and their application in China
Time:2020-07-08
-
Steel structure engineering introduces you to the classification of multi-tall steel structures and their stability design
Time:2020-07-08
-
Xirong's discussion on the application of foreign industrialized steel structure housing
Time:2020-07-08
-
The new environmental protection law makes the construction industry take a green path
Time:2020-07-08
-
Some problems and solutions in steel structure construction
Time:2020-07-08
-
The connecting materials of the steel structure project should meet the following requirements
Time:2020-07-08
-
Steel structure engineering introduces you to the 8 advantages of steel structure engineering
Time:2020-07-08
-
Do you know the difference between light steel room and color steel plate activity room in steel structure installation?
Time:2020-07-08
-
China's steel industry will not add new capacity until 2017
Time:2020-07-08
-
Steel structure engineering company on light steel structure residential performance analysis
Time:2020-07-08
-
Steel structure engineering is the best structural form of green building
Time:2020-07-08
-
Characteristics of long-span steel structure engineering
Time:2020-07-08
-
Green development of steel structure buildings
Time:2020-07-08
-
Three major strategies for steel structure development to break through the development bottleneck
Time:2020-07-08
-
Rainproof measures for rainy season construction of steel structure engineering
Time:2020-07-08
-
Three major obstacles to the development of steel structure construction enterprises
Time:2020-07-08
-
Steel structure building and its application in China
Time:2020-07-08
-
Steel structure installation technology and safety points
Time:2020-07-08
-
Take you into the steel structure manufacturer
Time:2020-07-08
-
Xirong tells you: steel structure fire protection measures
Time:2020-07-08
-
How to correctly choose steel for steel structure
Time:2020-07-08
-
Connection method and characteristics of steel structure
Time:2023-06-08
-
Types of steel structural steel beams
Time:2020-07-08
-
How to open up the market of steel structure engineering
Time:2020-07-08
-
Mianyang Steel Structure Company specifically analyzes product characteristics
Time:2020-07-08
-
Steel structure anti-corrosion tips
Time:2020-07-08
-
What are the deformation problems that steel structure companies tell you during processing?
Time:2020-07-08
-
Steel structure takes you to analyze steel structure translation installation technology
Time:2020-07-08
-
Steel structure Xirong staff training
Time:2020-07-08
-
The development of the steel structure engineering industry is considerable
Time:2020-07-08
-
Steel structure - new technology for steel structure housing
Time:2020-07-08
-
Yibin steel structure engineering company for everyone to introduce the steel tower mast structure
Time:2020-07-08
-
Steel Structure Company Analysis Steel Structure Engineering has received strong support from the government
Time:2020-07-08
-
Steel structure - anti-corrosion coating construction
Time:2020-07-08
-
Steel structure - sales personnel grade distinction
Time:2020-07-08
-
Personalized design of steel structure engineering company Kaiyuan
Time:2020-07-08
-
Arrangement and requirements of steel structure bolts
Time:2020-07-08
-
Steel Structure - Xirong Annual Meeting
Time:2020-07-08
-
Some industry issues considered by steel structure engineering companies
Time:2020-07-08
-
Steel structure - steel structure residential waterproof knowledge
Time:2020-07-08
-
Causes of steel structure damage and reinforcement technical measures
Time:2020-07-08
-
Data analysis of Chengdu Steel Structure Engineering Company
Time:2020-07-08
-
Sichuan steel structure - high-strength bolted connection inspection method
Time:2020-07-08
-
Sichuan steel structure - hoisting related knowledge and precautions
Time:2020-07-08
-
The problems faced by Chengdu steel structure manufacturers
Time:2020-07-08
-
Analysis of key points in the process of steel structure processing
Time:2020-07-08
-
Steel structure workshop design considerations
Time:2020-07-08
-
Chengdu Steel Structure Company has a more "humorous" side
Time:2020-07-08
-
Chengdu steel structure - rainy season steel structure construction measures
Time:2020-07-08
-
A funny Sichuan steel structure company
Time:2020-07-08
-
The influence of Sichuan Steel Structure Company
Time:2020-07-08
-
Chengdu Steel Structure Engineering Company's expansion of industry knowledge
Time:2020-07-08
-
Facing a different Sichuan steel structure engineering company
Time:2020-07-08
-
Issues that need to be paid attention to in steel structure construction (1)
Time:2020-07-08
-
Weekend heart, also take a look at Chengdu steel structure project
Time:2020-07-08
-
Precautions in steel structure construction (2)
Time:2020-07-08
-
What are the factors involved in Sichuan steel structure project?
Time:2020-07-08
-
Steel structure engineering indoor color plate condensation problem
Time:2020-07-08
-
Let you "stupid and moved" Sichuan steel structure engineering company service
Time:2020-07-08
-
In the continuous rainy season, how to construct the Sichuan steel structure project
Time:2020-07-08
-
From Double 11, talk about Sichuan steel structure project
Time:2020-07-08
-
Sichuan Steel Structure Engineering Company allows you to feel a different side
Time:2020-07-08
-
Precautions for construction land of Sichuan steel structure workshop
Time:2020-07-08
-
Take a look at the different Chengdu steel structure
Time:2020-07-08
-
What base material should be used for Sichuan steel structure? What is the composition and function of paint?
Time:2020-07-08
-
Maintenance and repair of steel structure glass roofing
Time:2020-07-08
-
Repair method of steel structure crack
Time:2020-07-08
-
Use ordinary methods to let you understand Chengdu steel structure engineering design
Time:2020-07-08
-
Steel structure is an important representative of green buildings
Time:2020-07-08
-
Steel structure rust removal method
Time:2020-07-08
-
The "unknown" side of Chengdu Steel Structure Company
Time:2020-07-08
-
Three methods of cooling steel structure workshop
Time:2020-07-08
-
Chengdu steel structure manufacturers are different
Time:2020-07-08
-
How to avoid potential safety hazards in steel structure workshops
Time:2020-07-08
-
Different Chengdu steel structure engineering service provider
Time:2020-07-08
-
Drainage system of steel structure workshop
Time:2020-07-08
-
Today's thunderstorm in Chengdu alarmed Chengdu Steel Structure Engineering Company
Time:2020-07-08
-
Chengdu steel structure engineering manufacturers take a different route
Time:2020-07-08
-
Three key points that steel structure anti-corrosion needs to pay attention to
Time:2020-07-08
-
Chengdu Steel Structure Engineering Company controls a new place
Time:2020-07-08
-
Technical knowledge of steel structure spraying
Time:2020-07-08
-
What are the advantages of steel structure
Time:2020-07-08
-
Several adjectives outline the good of the Xirong construction project
Time:2020-07-08
-
It turns out that the steel structure of the Sichuan steel structure project also has the effect of sound insulation!
Time:2020-07-08
-
Double 11, Xirong Construction Engineering Company makes you excited
Time:2020-07-08
-
It's winter, do you pay attention to Sichuan steel structure houses
Time:2020-07-08
-
The process of Sichuan steel structure engineering is no longer simple
Time:2020-07-08
-
Xirong construction project welcomes a new festival, guess what!
Time:2020-07-08
-
Different style Sichuan steel structure engineering manufacturers
Time:2020-07-08
-
See why many companies choose Xirong construction projects
Time:2020-07-08
-
Which is the best choice for Sichuan steel structure engineering facilities?
Time:2020-07-08
-
In today's fierce competition in the steel structure market, it is necessary to grasp the three major points of Sichuan steel structure engineering
Time:2020-07-08
-
Sichuan Xirong tells you why there are few high-rise steel structure houses?
Time:2020-07-08
-
Step 1 of steel structure engineering construction plan: steel structure foundation engineering
Time:2020-07-08
-
Step 2 of the steel structure engineering construction plan: steel structure hoisting
Time:2020-07-08
-
Steps 3 and 4 of the steel structure engineering construction plan: roofing, wall system installation and completion acceptance
Time:2020-07-08
-
Steps of the construction process of Sichuan steel structure
Time:2020-07-08
-
Introduction to steel structure engineering, mastering this knowledge is enough!
Time:2020-07-08
-
What are the main characteristics of Xirong steel structure engineering?
Time:2020-07-08
-
4 precautions for the calculation of steel structure engineering quantities
Time:2020-07-08
-
How to add points to the construction quality of the Chengdu steel structure workshop project?
Time:2020-07-08
-
Quality characteristics of steel structure engineering projects
Time:2020-07-08
-
Characteristics and regulations of Xirong steel structure engineering installation technology
Time:2020-07-08
-
What should I pay attention to in the professional contracting qualification of Chengdu steel structure engineering?
Time:2020-07-08
-
Few people know! The difference between steel structure engineering qualification and steel structure manufacturing qualification
Time:2020-07-08
-
Briefly describe the maintenance and maintenance of Sichuan steel structure workshop
Time:2020-07-08
-
Sichuan steel structure engineering design and construction experience summary!
Time:2020-07-08
-
Talk about the reinforcement methods of Sichuan steel structure workshop
Time:2020-07-08
-
Eight basic knowledge about Sichuan steel structure, worth collecting
Time:2020-07-08
-
About the construction quality of steel structure engineering projects
Time:2020-07-08
-
Do not want to work overtime, the following 4 points Sichuan steel structure engineering necessary skills
Time:2020-07-08
-
The safety problems and countermeasures in the construction of steel structure workshop are analyzed
Time:2020-07-08
-
Xirong - take you to understand the steel structure
Time:2020-07-08
-
Maintenance of steel structure engineering
Time:2020-07-08
-
Talking about the four major points of Sichuan steel structure engineering construction
Time:2020-07-08
-
Factors affecting the use of grid steel structure
Time:2020-07-08
-
Talking about the four major points of Sichuan steel structure engineering construction
Time:2020-07-08
-
Introduction to the characteristics of Chengdu steel structure
Time:2020-07-06
-
Introduction to the style of Chengdu decoration project
Time:2020-07-06
-
Introduction to the types of charging pile equipment in Chengdu
Time:2020-07-06
-
Introduction to the characteristics of Sichuan steel structure
Time:2020-07-06
-
Introduction to the characteristics of Sichuan steel structure
Time:2020-07-06
-
Introduction to the characteristics of Chengdu steel structure
Time:2023-06-05
-
Technical performance of Sichuan steel structure
Time:2020-07-06
-
Features of Chengdu steel structure
Time:2020-07-06
-
Technical performance of Chengdu steel structure
Time:2020-07-06
-
Introduction to the production method of Chengdu steel structure
Time:2020-07-06
-
Chengdu steel structure welding deformation and control correction
Time:2020-07-06
-
Chengdu decoration project reveals how to save money on the decoration of old houses
Time:2020-07-06
-
Chengdu steel structure analysis what is fireproof coating
Time:2020-07-06
-
Chengdu decoration project construction you need to know so much
Time:2020-07-06
-
How should we do a good job of anti-corrosion measures for the steel structure
Time:2020-07-06
-
Causes of steel structure damage and reinforcement technical measures
Time:2020-07-06
-
The charging pile is networked to realize the function
Time:2020-07-06
-
The main scope of use of steel structure
Time:2023-06-05
-
The superiority of Chengdu steel structure is reflected in where
Time:2020-07-06
-
Chengdu decoration project tells you that summer decoration has many benefits
Time:2020-07-06
-
Precautions for welding of steel structure construction
Time:2020-07-06
-
The difference between building decoration and decoration in Chengdu decoration project
Time:2020-07-06
-
What is the difference between Chengdu steel structure HN and HW
Time:2020-07-06
-
Chengdu steel structure construction attention problems
Time:2020-07-06
-
Chengdu steel structure must be made of fireproof coating
Time:2020-07-06
-
Characteristics of Chengdu steel structure application process
Time:2020-07-06
-
Chengdu steel structure project judgment how to judge
Time:2020-07-06
-
Chengdu steel structure building brings people a safe life
Time:2020-07-06
-
Installation of steel structure columns
Time:2020-07-06
-
Estimation skills for the amount of steel used in steel structure floors
Time:2020-07-06
-
Introduction to the characteristics of Chengdu steel structure
Time:2020-07-06
-
Introduction to the style of Chengdu decoration project
Time:2020-07-06
-
How to judge whether the membrane structure in Chengdu is qualified
Time:2020-07-06
-
What is the difference between public decoration and home improvement?
Time:2020-07-06
-
Sichuan curtain wall company shares the characteristics of glass curtain wall
Time:2020-07-06
-
Application characteristics of Chengdu glass curtain wall
Time:2020-07-06
-
Chengdu glass curtain wall is still an irreplaceable building material at this stage
Time:2020-07-06
-
Chengdu glass curtain wall maintenance and repair need to pay attention to!
Time:2020-07-06
-
What about the thermal insulation function of the glass curtain wall?
Time:2020-07-06
-
The difference between home decoration design and public decoration design
Time:2020-07-06
-
Introduction to the characteristics of Chengdu steel structure
Time:2020-07-06
-
Technical performance of Sichuan steel structure
Time:2020-07-06
-
Features of Chengdu steel structure
Time:2020-07-06
-
Introduction to the production method of Chengdu steel structure
Time:2020-07-06
-
Chengdu steel structure welding deformation and control correction
Time:2020-07-06
-
Chengdu decoration project reveals how to save money on the decoration of old houses
Time:2020-07-06
-
Chengdu steel structure analysis what is fireproof coating
Time:2020-07-06
-
What quality problems are prone to occur during the construction of steel structure engineering
Time:2020-07-06
-
Chengdu decoration project construction you need to know so much
Time:2020-07-06
-
How should we do a good job of anti-corrosion measures for the steel structure?
Time:2020-07-06
-
Chengdu steel structure pillar with spiral steel pipe manufacturer
Time:2020-07-06
-
Causes of steel structure damage and reinforcement technical measures
Time:2020-07-06
-
Chengdu steel structure charging pile network to realize the function
Time:2020-07-06
-
The main scope of use of Sichuan steel structure
Time:2020-07-06
-
The superiority of Chengdu steel structure is reflected in where
Time:2020-07-06
-
Chengdu decoration project tells you that summer decoration has many benefits
Time:2020-07-06
-
Precautions for welding of steel structure construction
Time:2020-07-06
-
The difference between building decoration and decoration in Chengdu decoration project
Time:2020-07-06
-
What is the difference between steel structure HN and HW?
Time:2020-07-06
-
Chengdu steel structure construction attention problems
Time:2020-07-06
-
Chengdu steel structure must be made of fireproof coating
Time:2020-07-06
-
Characteristics of Chengdu steel structure application process
Time:2020-07-06
-
Chengdu steel structure project judgment how to judge
Time:2020-07-06
-
Chengdu steel structure building brings people a safe life
Time:2020-07-06
-
Installation of steel structure columns in Chengdu
Time:2020-07-06
-
There are 11 regulations that should be met by the quality acceptance of steel structure engineering in Chengdu
Time:2020-07-06
-
There are a few points to pay attention to when building a steel structure staircase
Time:2020-07-06
-
What are the reasons that affect the cost of steel structure engineering?
Time:2020-07-06
-
How to use Sichuan steel structure for roof construction
Time:2020-07-06
-
Chengdu steel structure workshop processing should pay attention to strength, plasticity and toughness
Time:2020-07-06
-
How to use steel structure for roof construction
Time:2020-07-06
-
Seismic construction method of intercolumn support of steel structure workshop
Time:2020-07-06
-
These two points are very important to build a steel structure workshop
Time:2020-07-06
-
Pay attention to these problems, the quality of steel structure construction has been greatly improved
Time:2020-07-06
-
What is the difference between H-beam and I-beam for steel structure buildings?
Time:2020-07-06
-
What are the measures to prevent deviations in the installation of steel structures
Time:2020-07-06
-
Steel structure grid roof construction scheme
Time:2020-04-24
-
Illustrate the basic knowledge of steel structure engineering
Time:2020-04-24
-
How long does a steel structure house last life?
Time:2020-04-24
-
Analysis of the advantages and characteristics of steel truss floor bearing plate
Time:2020-04-24
-
On the difference and advantages and disadvantages between steel truss floor bearing plate and ordinary floor bearing plate
Time:2020-04-24


