Steel structure grid roof construction scheme
Category: Industry News
Time:2020-04-24
Installation of the skeleton (or purlin).
Depending on the skeleton material, the construction tools are different. There are roughly the following mechanical equipment: electric welding machine, grinding wheel cutting machine, profile cutting machine, angle grinder, pistol drill, switchboard, power cord, hose glue gun and small hardware tools.
The construction sequence of this project: component correction→ rust removal→ lofting number material→ blanking and forming→ installation and welding.
The roof purlins of this project are made of light steel such as steel square and C-shaped steel, because light steel often bends and warps during transportation and stacking, so after the material enters the site, it is first straightened and leveled, and the site uses a wrench bender or manual correction work.
Before removing rust from the skeleton material, dust and dirt should be removed from the surface of the steel. The rust removal of the steel components of this project adopts a combination of manual and electrical tools. After the rust removal work is completed, the anti-rust primer should be brushed or sprayed again.
According to the drawing size, the C-shaped steel (or square tong) is cut to the appropriate length with a grinding wheel cutting machine, and then the skeleton is welded. The welding process uses AC arc welding machine and E43 series, and in order to prevent defects such as meat bite and welding head, small current and small diameter electrode (2.5-3.0mm) are used for welding. And use auxiliary fixtures and fixtures to ensure the accuracy of the geometric dimensions of the structure.
The steel skeleton is tested and corrected with a level and the steel wire. The production process should be measured and corrected at any time, and the deformation should be controlled within the allowable range. The skeleton and the support pallet surface are welded together, and the skeleton production can assemble and weld a part of the skeleton, and then lift it to the support pallet for welding firmly, or it can be directly assembled and welded on the support pallet, and the skeleton in the same slope direction should be on one surface.
After the skeleton is made and installed, dust, iron filings, oil, etc. on the surface of the skeleton should be removed. According to the requirements of the drawing, brush the anti-rust paint, and then brush the topcoat and protective paint after the anti-rust paint is completely dry. For the metal skeleton of the roof, the coating generally adopts two methods: manual brushing and air spraying.
The coating work is carried out immediately following the grid installation and keel installation, the coating worker should be equipped with a thermometer and thickness tester, the topcoat is manually brushed on site, should not leak, the optimal temperature of construction should be 5-30 degrees, and the humidity is not higher than 85%. Do not brush on rainy days. Brushing should be divided into batches at intervals of 12 hours, and the brushing should not be too thick at one time to prevent flow marks. The ventilation environment should be good during construction, and attention should be paid to avoiding open flames. During the production of purlin skeletons, roof panels and perimeter enclosure materials should be prepared in time to avoid delaying the construction period.
Installation of roofing and enclosures
The roof mainly adopts 50mm thick sandwich panels, and the length of the roof panel depends on the engineering needs and transportation requirements. The installation adopts hidden buckle connection, the use of self-tapping nails fixed on the purlin, the installed profiled steel plate requires tight lap, the roof panel corrugation is guaranteed to be perpendicular to the ridge axis, and a straight line is pre-placed with a measuring instrument to determine the arrangement of the overall plate.
In large construction projects, in order to shorten the time, the bundled roof panels can be lifted directly from the truck to the roof frame by crane, and for longer slabs, the method of flat stretcher and hanging rope is recommended. For small and medium-sized projects, it can be unloaded by hand, and then a single roof panel can be tied with ropes, and then the roof panel is pulled to the roof frame by manpower, and then fixed and installed. This project adopts manual handling construction.
In order to protect the surface of the laminated steel plate on the roof panel and ensure the safety of the construction personnel, the laminated steel plate must be touched with dry and clean gloves. Do not drag the roof panel surface laminated steel plate on the rough surface or the roof panel laminated steel plate, and other things such as tools can not be dragged on the surface of the roof panel laminated steel plate.
When walking longitudinally along the roof panel, walk in its groove, and when walking laterally along the roof panel, try to get as close to or step on the roof support point as possible. In general, the load should be distributed evenly on the soles of the feet as much as possible, not concentrated on the heels or toes. Wear soft-soled flats, not strip-notched sols, which tend to be embedded in small pebbles. The surface of the newly dismantled roof panel laminated steel plate is greasy. Be very careful when acting. It is inevitable to cut the surface laminated steel plate of the roof panel on the construction site, but care should be taken to protect other plates, because the chainsaw cutting will produce metal particles. If it must be cut on other roof surface laminated steel plates, a protective object should be placed between the cut roof surface laminated steel plate and the lower roof panel surface laminated steel plate, and the roof panel surface laminated steel plate should be face down, and it is best to put a metal cutting knife in the chainsaw. Compared to emery wheel cutting, this results in fewer metal particles and a smoother cutout.
In general roofing and flashing board installation operations, self-tapping bolts, drilling, hand saws, chainsaws, or other operations will leave metal debris in the adjacent areas of the roof, and these debris and other debris (rivets, iron nails, screws, etc.) must be eliminated from the roof, flashing board, gutter, etc. as soon as possible. Make this work the end of the day. Especially after the installation of the entire roof, it cannot be exempted. Neglecting this work will oxidize the metal debris and cause the surface to form a stain. When iron, copper, lead, etc. as the base material of the article and the surface of the aluminum-zinc plated sheet are in contact with the surface of the galvanized sheet, and are jointly exposed to moisture or condensation, it will cause the damage of the aluminum-zinc layer and lead to corrosion of the steel plate from the surface.
When lifting the roof surface laminate steel plate tothe level ready to start the installation, please pay attention to ensure that all the roof surface laminate steel plate is facing up and all lap edges are facing the roof side to be installed. Otherwise, not only will the roof panel surface laminate steel plate be flipped, but also the roof panel surface laminated steel plate will turn around. Bales of laminated steel panels on the roof panel shall be placed close to or placed on the purlin support point, not in the purlin span, and before fixing the first plate, ensure that its position is vertical and square, and that it falls correctly in relation to other building elements.
When the first roof panel surface laminated steel plate isfixed in place, a continuous collimator is pulled at the lower end of the roof, and this line and the first roof panel surface laminated steel plate will become the conductor, which is convenient for the rapid installation and correction of subsequent roof panel surface laminated steel plates. Then, each roof area is to be tested in a fixed section during installation, by measuring the width of the laminated steel plate on the surface of the fixed roofing panel, once at its top and once at the bottom, to ensure that there is no movement and fan. At certain stages, such as halfway through installation, the distance from the top and bottom of the fixed roof surface laminate steel plate to the far edge of the roof or the finish line is also measured to ensure that the fixed roof surface laminated steel plate is parallel to the finish line. If adjustments are required, each plate can be placed and fixed later for slight sector adjustment. Until the roof surface laminate steel plate reaches flatness. According to the construction drawings, the grid roof panels are stacked on the material stacking yard in a complete set, and the complete sets of grid roof panels are hoisted to the design position and fixed with the crane.
Theconnection of color steel plate and steel structure purlins should use bolts or self-tapping screws. When using bolts, a larger piece should be used, and the tightening force should be moderate and firm to avoid pitfalls in the connection fastening point. The bolts of the wall should be neat. Symmetrical, evenly spaced. The color steel plate used for the corner, that is, the corner plate should be marked in detail on the construction drawing, and the construction should be carried out according to the drawing. The inner outer corner of the corner plate should use color steel corner plate or angle aluminum, and its butt joint should be flat and dense, and the wall surface of the color steel plate should be kept smooth and vertical. The connections at the corners of the corner plates should be neat and consistent. Level. The vertical direction should be in a straight line, there should be no obvious depression at the connection without obvious misalignment, and no wavy warpage should occur after the inner outer corner edge is connected. During installation and construction, in addition to complying with the relevant technical requirements of roof waterproofing engineering, the roof waterproofing project should also comply with the following principles:
1) The slope of the roof shall not be less than 5%, and the corrosion environment shall not be less than 8%.
2) The roof panels shall not be overlapped when conditions permit. When lapping is necessary, it should be lapped in the long direction of the slope, and the lap point must fall on the purlin or support. When the roof slope is less than or equal to 10%, the lap length is not less than 250mm, and when the roof slope is greater than 10%, the lap length should not be less than 180mm. The lap steel plate part should be connected with stitching nails or pull rivets, and the middle distance should not be greater than 300mm. All lap joints must be sealed with sealing paste or waterproof material, and exposed nail heads should be waterproof. Where the roof panels that must be lapped in the long direction of the slope, the concealed buckle pattern plate is the first to push. Use self-tapping nails to fix the special fixation seat of the dark gusset plate on the purlin, and then lay the dark gusset plate on the special support, and clamp the lap part with a special fixture at the crest of the plate, and the plate is fixed as a whole. During the construction process, pull rivets or self-tapping nails can not be punched at the valley to avoid roof water seepage or leakage, the lateral lap of the roof panel (corrugated type) should be consistent with the dominant direction, and the lap part must be set with waterproof sealing material.
Wrapped corner watercolor steel plate. The lap of the eaves dripping watercolor steel plate and other accessories should be crimped in the leeward direction or along the water direction as much as possible, and the crimping length should not be less than 60mm, which can be connected with pull rivets, and its spacing should not be greater than 200mm, and the side seam should be straight when installing. The roof panel should avoid opening holes as much as possible, and when holes must be opened, they should be in accordance with the design requirements and do corresponding technical treatment.
Maintenance and repair of glass roofing
1. Maintenance
(1) After the acceptance and delivery of the glass roofing project, the user unit should formulate the maintenance and repair plan and system of the roof in time.
(2) The maintenance of the roof should be carried out in accordance with the following requirements.
a. According to the roof area and the degree of ash pollution, determine the number and cycle of cleaning the roof, which should be every year
Wash at least once.
b. The mechanical equipment for cleaning the roof (such as the washing machine) should be flexible and convenient to operate so as not to scratch the roof
Glass.
2. Maintenance
(1) If the metal skeleton finds that the bolt is loose, it should be tightened or welded firmly. When rust is found to be on the connectors, it should be removed and repainted.
(2) If the glass is found to be loose or damaged, it should be repaired or replaced in time.
(3) When the sealant and sealing strip are found to be falling off or damaged, they should be repaired and replaced in time.
(4) When it is found that the anchorage of the main skeleton structure is loose or falling off, it should be replaced or taken measures to strengthen and repair it in time.
(5) Regularly check the drainage system and dredge it in time if blockages are found.
(6) When the glass roof is in normal use, a comprehensive inspection should be carried out every 5 years.
Roof enclosure
The following safety regulations should be met in the maintenance and repair of roofs:
a. Inspection, maintenance and repair shall not be carried out in wind power above grade 4 and heavy rain.
b. The machinery used for cleaning and maintenance must be firm, easy to operate, safe and reliable.
c. In the maintenance and repair work, all those who work at height must comply with the relevant provisions of the current national standard "Safety Technical Code for Work at Height in Building Construction" (JGJ80).
Keywords: Steel structure grid roof construction scheme
Related Information
Company News
-
Xirong "brand Great Wall board - Southwest Great Wall in the field of home decoration insulation board
Time:2024-08-06
-
Welcome the bid for steel structure enclosure materials for the "West China Intelligent Assembly Base Project" at the beginning of 2024
Time:2024-04-15
-
Shifang Navigation Industrial Park - Tianhe Solar's 160000 ㎡ Steel Bar Truss Floor Support Plate Project Celebrates Completion
Time:2024-04-15
-
Congratulations on winning the bid for "Meikou Chengdu Qingbaijiang Cold Chain Supply Chain Construction Project"
Time:2022-11-08
-
The Zerui comprehensive insurance project started successfully
Time:2022-11-08
-
The 200,000 square meters of truss floor bearing materials for the Chengdu Aviation Industrial Park project continued to be delivered
Time:2022-11-07
-
Notice of the Department of Housing and Urban-Rural Development of Sichuan Province on the use of the "Certificate of Qualification for Job Training and Assessment of Professionals in the Field of Housing and Urban-Rural Construction"
Time:2021-12-28
-
Notice of the General Office of the Ministry of Housing and Urban-Rural Development on matters related to the unified renewal of the qualifications of construction project enterprises
Time:2021-12-18
-
A pearl of performance on the prairie
Time:2021-09-06
-
Celebrating the 100th anniversary of the founding of the party, the Chengdu metal cloud merchant headquarters and regional center project started construction in the scorching summer and braved the wind and rain
Time:2021-07-12
-
Celebrating Sichuan Qingyuan Construction Engineering settled in the "China Building Science and Technology Conference and Construction Expo"
Time:2021-07-05
-
Happy birthday!
Time:2021-07-01
-
Morning meeting
Time:2021-06-23
-
2021 company safety fire drill
Time:2021-06-17
-
Leaders of Wuxi Binhu District visited the chairman unit of Chengdu Yancheng Chamber of Commerce for inspection
Time:2021-06-04
-
The large-scale cross-line municipal steel bridge project in Kaili City, Qiandongnan Prefecture, Guizhou Province was officially hoisted
Time:2020-06-03
-
Greenland Southwest Operation and Settlement Center for Global Imported Commodities reached a cooperation with Xirong Group
Time:2020-06-03
-
Silhouette of the steel structure construction site of PepsiCo Food (Sichuan) production base construction project
Time:2020-06-03
-
Zhengxi Robot R&D and Manufacturing Base Construction Project The resumption of construction work was carried out in an orderly manner
Time:2020-06-03
-
Qingbaijiang Sino-Ocean International Cold Chain E-commerce Logistics Park steel structure project welcomes the resumption of work
Time:2020-06-03
-
Sichuan TV Science and Education Channel "Impact Sichuan" interviewed Sichuan Qingyuan Construction Engineering Co., Ltd
Time:2020-06-03
-
On February 20, 2020, the leaders of the District CPPCC and the Industrial Management Committee inspected the resumption of work and epidemic prevention in our company
Time:2020-06-03
-
Notice of official resumption of work
Time:2020-06-03
-
Silhouette of the steel structure construction site of PepsiCo Food (Sichuan) production base construction project
Time:2020-04-24
Industry News
-
Carey is about to give birth to a new landmark of Internet celebrities, panoramic VR sneak peek!
Time:2020-07-08
-
Xirong takes you to understand the five characteristics of doors and windows
Time:2020-07-08
-
Xi Rong tells you how steel is developing in the Chinese market?
Time:2020-07-08
-
The steel structure engineering company reminds you of the processing precautions of the color coated plate
Time:2020-07-08
-
Xirong Steel Structure Company announces industry trends
Time:2020-07-08
-
What problems do you need to pay attention to when building color steel?
Time:2020-07-08
-
Steel structure engineering company takes you to focus on the development trend of color steel plate
Time:2020-07-08
-
Analysis of the current situation of marketing channels in China's construction machinery industry
Time:2020-07-08
-
The steel structure engineering company summarizes the use characteristics of galvanized channel steel for you
Time:2020-07-08
-
The steel structure engineering company tells you how to go out of the domestic steel structure
Time:2020-07-08
-
Steel structure engineering company tells you why China's steel prices are rising again?
Time:2020-07-08
-
Do you understand the "breaking" and "standing" of the development of the steel industry?
Time:2020-07-08
-
Xirong takes you to understand the "three magic weapons" in steel trade marketing
Time:2020-07-08
-
Xirong talks about CAI steel market will turn salted fish over?
Time:2020-07-08
-
Steel structure engineering company analysis steel price rise is difficult to end
Time:2020-07-08
-
How can the steel industry break the "curse" of financial difficulties?
Time:2020-07-08
-
Xirong analyzes modern steel structure buildings and their application in China
Time:2020-07-08
-
Steel structure engineering introduces you to the classification of multi-tall steel structures and their stability design
Time:2020-07-08
-
Xirong's discussion on the application of foreign industrialized steel structure housing
Time:2020-07-08
-
The new environmental protection law makes the construction industry take a green path
Time:2020-07-08
-
Some problems and solutions in steel structure construction
Time:2020-07-08
-
The connecting materials of the steel structure project should meet the following requirements
Time:2020-07-08
-
Steel structure engineering introduces you to the 8 advantages of steel structure engineering
Time:2020-07-08
-
Do you know the difference between light steel room and color steel plate activity room in steel structure installation?
Time:2020-07-08
-
China's steel industry will not add new capacity until 2017
Time:2020-07-08
-
Steel structure engineering company on light steel structure residential performance analysis
Time:2020-07-08
-
Steel structure engineering is the best structural form of green building
Time:2020-07-08
-
Characteristics of long-span steel structure engineering
Time:2020-07-08
-
Green development of steel structure buildings
Time:2020-07-08
-
Three major strategies for steel structure development to break through the development bottleneck
Time:2020-07-08
-
Rainproof measures for rainy season construction of steel structure engineering
Time:2020-07-08
-
Three major obstacles to the development of steel structure construction enterprises
Time:2020-07-08
-
Steel structure building and its application in China
Time:2020-07-08
-
Steel structure installation technology and safety points
Time:2020-07-08
-
Take you into the steel structure manufacturer
Time:2020-07-08
-
Xirong tells you: steel structure fire protection measures
Time:2020-07-08
-
How to correctly choose steel for steel structure
Time:2020-07-08
-
Connection method and characteristics of steel structure
Time:2023-06-08
-
Types of steel structural steel beams
Time:2020-07-08
-
How to open up the market of steel structure engineering
Time:2020-07-08
-
Mianyang Steel Structure Company specifically analyzes product characteristics
Time:2020-07-08
-
Steel structure anti-corrosion tips
Time:2020-07-08
-
What are the deformation problems that steel structure companies tell you during processing?
Time:2020-07-08
-
Steel structure takes you to analyze steel structure translation installation technology
Time:2020-07-08
-
Steel structure Xirong staff training
Time:2020-07-08
-
The development of the steel structure engineering industry is considerable
Time:2020-07-08
-
Steel structure - new technology for steel structure housing
Time:2020-07-08
-
Yibin steel structure engineering company for everyone to introduce the steel tower mast structure
Time:2020-07-08
-
Steel Structure Company Analysis Steel Structure Engineering has received strong support from the government
Time:2020-07-08
-
Steel structure - anti-corrosion coating construction
Time:2020-07-08
-
Steel structure - sales personnel grade distinction
Time:2020-07-08
-
Personalized design of steel structure engineering company Kaiyuan
Time:2020-07-08
-
Arrangement and requirements of steel structure bolts
Time:2020-07-08
-
Steel Structure - Xirong Annual Meeting
Time:2020-07-08
-
Some industry issues considered by steel structure engineering companies
Time:2020-07-08
-
Steel structure - steel structure residential waterproof knowledge
Time:2020-07-08
-
Causes of steel structure damage and reinforcement technical measures
Time:2020-07-08
-
Data analysis of Chengdu Steel Structure Engineering Company
Time:2020-07-08
-
Sichuan steel structure - high-strength bolted connection inspection method
Time:2020-07-08
-
Sichuan steel structure - hoisting related knowledge and precautions
Time:2020-07-08
-
The problems faced by Chengdu steel structure manufacturers
Time:2020-07-08
-
Analysis of key points in the process of steel structure processing
Time:2020-07-08
-
Steel structure workshop design considerations
Time:2020-07-08
-
Chengdu Steel Structure Company has a more "humorous" side
Time:2020-07-08
-
Chengdu steel structure - rainy season steel structure construction measures
Time:2020-07-08
-
A funny Sichuan steel structure company
Time:2020-07-08
-
The influence of Sichuan Steel Structure Company
Time:2020-07-08
-
Chengdu Steel Structure Engineering Company's expansion of industry knowledge
Time:2020-07-08
-
Facing a different Sichuan steel structure engineering company
Time:2020-07-08
-
Issues that need to be paid attention to in steel structure construction (1)
Time:2020-07-08
-
Weekend heart, also take a look at Chengdu steel structure project
Time:2020-07-08
-
Precautions in steel structure construction (2)
Time:2020-07-08
-
What are the factors involved in Sichuan steel structure project?
Time:2020-07-08
-
Steel structure engineering indoor color plate condensation problem
Time:2020-07-08
-
Let you "stupid and moved" Sichuan steel structure engineering company service
Time:2020-07-08
-
In the continuous rainy season, how to construct the Sichuan steel structure project
Time:2020-07-08
-
From Double 11, talk about Sichuan steel structure project
Time:2020-07-08
-
Sichuan Steel Structure Engineering Company allows you to feel a different side
Time:2020-07-08
-
Precautions for construction land of Sichuan steel structure workshop
Time:2020-07-08
-
Take a look at the different Chengdu steel structure
Time:2020-07-08
-
What base material should be used for Sichuan steel structure? What is the composition and function of paint?
Time:2020-07-08
-
Maintenance and repair of steel structure glass roofing
Time:2020-07-08
-
Repair method of steel structure crack
Time:2020-07-08
-
Use ordinary methods to let you understand Chengdu steel structure engineering design
Time:2020-07-08
-
Steel structure is an important representative of green buildings
Time:2020-07-08
-
Steel structure rust removal method
Time:2020-07-08
-
The "unknown" side of Chengdu Steel Structure Company
Time:2020-07-08
-
Three methods of cooling steel structure workshop
Time:2020-07-08
-
Chengdu steel structure manufacturers are different
Time:2020-07-08
-
How to avoid potential safety hazards in steel structure workshops
Time:2020-07-08
-
Different Chengdu steel structure engineering service provider
Time:2020-07-08
-
Drainage system of steel structure workshop
Time:2020-07-08
-
Today's thunderstorm in Chengdu alarmed Chengdu Steel Structure Engineering Company
Time:2020-07-08
-
Chengdu steel structure engineering manufacturers take a different route
Time:2020-07-08
-
Three key points that steel structure anti-corrosion needs to pay attention to
Time:2020-07-08
-
Chengdu Steel Structure Engineering Company controls a new place
Time:2020-07-08
-
Technical knowledge of steel structure spraying
Time:2020-07-08
-
What are the advantages of steel structure
Time:2020-07-08
-
Several adjectives outline the good of the Xirong construction project
Time:2020-07-08
-
It turns out that the steel structure of the Sichuan steel structure project also has the effect of sound insulation!
Time:2020-07-08
-
Double 11, Xirong Construction Engineering Company makes you excited
Time:2020-07-08
-
It's winter, do you pay attention to Sichuan steel structure houses
Time:2020-07-08
-
The process of Sichuan steel structure engineering is no longer simple
Time:2020-07-08
-
Xirong construction project welcomes a new festival, guess what!
Time:2020-07-08
-
Different style Sichuan steel structure engineering manufacturers
Time:2020-07-08
-
See why many companies choose Xirong construction projects
Time:2020-07-08
-
Which is the best choice for Sichuan steel structure engineering facilities?
Time:2020-07-08
-
In today's fierce competition in the steel structure market, it is necessary to grasp the three major points of Sichuan steel structure engineering
Time:2020-07-08
-
Sichuan Xirong tells you why there are few high-rise steel structure houses?
Time:2020-07-08
-
Step 1 of steel structure engineering construction plan: steel structure foundation engineering
Time:2020-07-08
-
Step 2 of the steel structure engineering construction plan: steel structure hoisting
Time:2020-07-08
-
Steps 3 and 4 of the steel structure engineering construction plan: roofing, wall system installation and completion acceptance
Time:2020-07-08
-
Steps of the construction process of Sichuan steel structure
Time:2020-07-08
-
Introduction to steel structure engineering, mastering this knowledge is enough!
Time:2020-07-08
-
What are the main characteristics of Xirong steel structure engineering?
Time:2020-07-08
-
4 precautions for the calculation of steel structure engineering quantities
Time:2020-07-08
-
How to add points to the construction quality of the Chengdu steel structure workshop project?
Time:2020-07-08
-
Quality characteristics of steel structure engineering projects
Time:2020-07-08
-
Characteristics and regulations of Xirong steel structure engineering installation technology
Time:2020-07-08
-
What should I pay attention to in the professional contracting qualification of Chengdu steel structure engineering?
Time:2020-07-08
-
Few people know! The difference between steel structure engineering qualification and steel structure manufacturing qualification
Time:2020-07-08
-
Briefly describe the maintenance and maintenance of Sichuan steel structure workshop
Time:2020-07-08
-
Sichuan steel structure engineering design and construction experience summary!
Time:2020-07-08
-
Talk about the reinforcement methods of Sichuan steel structure workshop
Time:2020-07-08
-
Eight basic knowledge about Sichuan steel structure, worth collecting
Time:2020-07-08
-
About the construction quality of steel structure engineering projects
Time:2020-07-08
-
Do not want to work overtime, the following 4 points Sichuan steel structure engineering necessary skills
Time:2020-07-08
-
The safety problems and countermeasures in the construction of steel structure workshop are analyzed
Time:2020-07-08
-
Xirong - take you to understand the steel structure
Time:2020-07-08
-
Maintenance of steel structure engineering
Time:2020-07-08
-
Talking about the four major points of Sichuan steel structure engineering construction
Time:2020-07-08
-
Factors affecting the use of grid steel structure
Time:2020-07-08
-
Talking about the four major points of Sichuan steel structure engineering construction
Time:2020-07-08
-
Introduction to the characteristics of Chengdu steel structure
Time:2020-07-06
-
Introduction to the style of Chengdu decoration project
Time:2020-07-06
-
Introduction to the types of charging pile equipment in Chengdu
Time:2020-07-06
-
Introduction to the characteristics of Sichuan steel structure
Time:2020-07-06
-
Introduction to the characteristics of Sichuan steel structure
Time:2020-07-06
-
Introduction to the characteristics of Chengdu steel structure
Time:2023-06-05
-
Technical performance of Sichuan steel structure
Time:2020-07-06
-
Features of Chengdu steel structure
Time:2020-07-06
-
Technical performance of Chengdu steel structure
Time:2020-07-06
-
Introduction to the production method of Chengdu steel structure
Time:2020-07-06
-
Chengdu steel structure welding deformation and control correction
Time:2020-07-06
-
Chengdu decoration project reveals how to save money on the decoration of old houses
Time:2020-07-06
-
Chengdu steel structure analysis what is fireproof coating
Time:2020-07-06
-
Chengdu decoration project construction you need to know so much
Time:2020-07-06
-
How should we do a good job of anti-corrosion measures for the steel structure
Time:2020-07-06
-
Causes of steel structure damage and reinforcement technical measures
Time:2020-07-06
-
The charging pile is networked to realize the function
Time:2020-07-06
-
The main scope of use of steel structure
Time:2023-06-05
-
The superiority of Chengdu steel structure is reflected in where
Time:2020-07-06
-
Chengdu decoration project tells you that summer decoration has many benefits
Time:2020-07-06
-
Precautions for welding of steel structure construction
Time:2020-07-06
-
The difference between building decoration and decoration in Chengdu decoration project
Time:2020-07-06
-
What is the difference between Chengdu steel structure HN and HW
Time:2020-07-06
-
Chengdu steel structure construction attention problems
Time:2020-07-06
-
Chengdu steel structure must be made of fireproof coating
Time:2020-07-06
-
Characteristics of Chengdu steel structure application process
Time:2020-07-06
-
Chengdu steel structure project judgment how to judge
Time:2020-07-06
-
Chengdu steel structure building brings people a safe life
Time:2020-07-06
-
Installation of steel structure columns
Time:2020-07-06
-
Estimation skills for the amount of steel used in steel structure floors
Time:2020-07-06
-
Introduction to the characteristics of Chengdu steel structure
Time:2020-07-06
-
Introduction to the style of Chengdu decoration project
Time:2020-07-06
-
How to judge whether the membrane structure in Chengdu is qualified
Time:2020-07-06
-
What is the difference between public decoration and home improvement?
Time:2020-07-06
-
Sichuan curtain wall company shares the characteristics of glass curtain wall
Time:2020-07-06
-
Application characteristics of Chengdu glass curtain wall
Time:2020-07-06
-
Chengdu glass curtain wall is still an irreplaceable building material at this stage
Time:2020-07-06
-
Chengdu glass curtain wall maintenance and repair need to pay attention to!
Time:2020-07-06
-
What about the thermal insulation function of the glass curtain wall?
Time:2020-07-06
-
The difference between home decoration design and public decoration design
Time:2020-07-06
-
Introduction to the characteristics of Chengdu steel structure
Time:2020-07-06
-
Technical performance of Sichuan steel structure
Time:2020-07-06
-
Features of Chengdu steel structure
Time:2020-07-06
-
Introduction to the production method of Chengdu steel structure
Time:2020-07-06
-
Chengdu steel structure welding deformation and control correction
Time:2020-07-06
-
Chengdu decoration project reveals how to save money on the decoration of old houses
Time:2020-07-06
-
Chengdu steel structure analysis what is fireproof coating
Time:2020-07-06
-
What quality problems are prone to occur during the construction of steel structure engineering
Time:2020-07-06
-
Chengdu decoration project construction you need to know so much
Time:2020-07-06
-
How should we do a good job of anti-corrosion measures for the steel structure?
Time:2020-07-06
-
Chengdu steel structure pillar with spiral steel pipe manufacturer
Time:2020-07-06
-
Causes of steel structure damage and reinforcement technical measures
Time:2020-07-06
-
Chengdu steel structure charging pile network to realize the function
Time:2020-07-06
-
The main scope of use of Sichuan steel structure
Time:2020-07-06
-
The superiority of Chengdu steel structure is reflected in where
Time:2020-07-06
-
Chengdu decoration project tells you that summer decoration has many benefits
Time:2020-07-06
-
Precautions for welding of steel structure construction
Time:2020-07-06
-
The difference between building decoration and decoration in Chengdu decoration project
Time:2020-07-06
-
What is the difference between steel structure HN and HW?
Time:2020-07-06
-
Chengdu steel structure construction attention problems
Time:2020-07-06
-
Chengdu steel structure must be made of fireproof coating
Time:2020-07-06
-
Characteristics of Chengdu steel structure application process
Time:2020-07-06
-
Chengdu steel structure project judgment how to judge
Time:2020-07-06
-
Chengdu steel structure building brings people a safe life
Time:2020-07-06
-
Installation of steel structure columns in Chengdu
Time:2020-07-06
-
There are 11 regulations that should be met by the quality acceptance of steel structure engineering in Chengdu
Time:2020-07-06
-
There are a few points to pay attention to when building a steel structure staircase
Time:2020-07-06
-
What are the reasons that affect the cost of steel structure engineering?
Time:2020-07-06
-
How to use Sichuan steel structure for roof construction
Time:2020-07-06
-
Chengdu steel structure workshop processing should pay attention to strength, plasticity and toughness
Time:2020-07-06
-
How to use steel structure for roof construction
Time:2020-07-06
-
Seismic construction method of intercolumn support of steel structure workshop
Time:2020-07-06
-
These two points are very important to build a steel structure workshop
Time:2020-07-06
-
Pay attention to these problems, the quality of steel structure construction has been greatly improved
Time:2020-07-06
-
What is the difference between H-beam and I-beam for steel structure buildings?
Time:2020-07-06
-
What are the measures to prevent deviations in the installation of steel structures
Time:2020-07-06
-
Steel structure grid roof construction scheme
Time:2020-04-24
-
Illustrate the basic knowledge of steel structure engineering
Time:2020-04-24
-
How long does a steel structure house last life?
Time:2020-04-24
-
Analysis of the advantages and characteristics of steel truss floor bearing plate
Time:2020-04-24
-
On the difference and advantages and disadvantages between steel truss floor bearing plate and ordinary floor bearing plate
Time:2020-04-24